Effluent Sample 7/16/15 

Analysis of Hydro, OK WWTP Effluent for BOD, CBOD and TSS 

Date
Permit Limits
 BOD
20 mg/L
CBODTSS
30 mg/L
Lab Performing Analysis
12/20/2013 Influent 165   171 CAL
  Effluent 7   9 CAL
2/24/2014 Influent 254 223 350 CAL
  Effluent 15 11 17 CAL
6/13/2014 Influent 166 151 158 CAL
  Effluent 14 5 15 CAL
11/13/2014 Influent 226 206 48 CAL
  Effluent 3 2.8 8.5 CAL
5/28/2015 Influent 140 119 332 CAL
  Effluent 3 3 10 CAL

CAL—Colorado Analytical Laboratories, Inc.

 

Analysis of Hydro, OK WWTP Effluent for Fecal Coliforms

Date
Permit Limits
CFU/100 mL
200 CFU/100 mL
Lab Performing Analysis
2/26/2014 <10 ETI
5/2/2014 52 ETI
6/3/2014 10 ETI
7/15/2014 <10 ETI
8/12/2014 10 ETI
9/16/2014 <10 ETI
5/12/2015 <10 ETI
6/4/2015 <10 ETI

ETI--Environmental Testing, Inc, of Oklahoma City, OK

 

Analysis of Hydro, OK WWTP Effluent for NH3 and PO4

DateInfluent NH3Effluent NH3TemperatureEffluent PO4Lab Performing Analysis
10/21/2013    0.11     1.17 CAL 
11/4/2013   0.44     CAL
11/20/2013   0.43   0.83 CAL
2/6/2014 28.4 0.58 30oF   AES
3/7/2014 18.0 0.09 41oF   AES
5/23/2014       0.87 CAL
6/13/2014       0.46 CAL 
8/7/2014       1.34 CAL
11/13/2014 14.5 0.09     CAL
12/9/2014 17.5 0.4    0.3  AES
5/28/2015       0.52 CAL
CAL—Colorado Analytical Laboratories, Inc.
AES—Anthony’s Environmental Services
Hydro has no current permit limits for NH3 and PO4

 

Icing on Pond—February 6, 2014

Icing on Pond

 

Analysis of Samples Taken From Hydro Facility—February 6, 2014 

 BODTSSNH3Water Temp
Influent     28.4 mg/L  
Effluent 6.3 mg/L 9.0 mg/L 0.28 mg/L 30o F

 

Illegal Discharge of Oil Pollutant—April 4, 2014

Illegal discharge of pollutant

Influent from City was diverted into empty concrete clarifying tanks, previously used at WWTP. Picture shows pollutant being pumped using a self-priming centrifugal pump from cell into clarifying tanks. 

Centrifugal pump

 

Oil Pollutant Residue After Solid Separation Process in the EC Building 

Oil pollutant residue after separation process

 

Before and After Treatment Samples

Sample of before and after 

The WWTP experienced a second instance of illegal discharge of oil pollutant in April, 2015.  In each instance, the combined technologies of BiO2 Biological Treatment Process and Electrocoagulation allowed the City to avoid the high cost of pumping and hauling the pollutant to a Hazardous Waste Facility and stay in compliance with their permit limits.

Hydro WWTP CAPEX and OPEX Feasibility Analysis

Feasibility by Third Party Engineering Firm
(based on .3 MGD design flow)
(2011 Pricing)

SYSTEM CAPEX COSTS

System Capex Costs 

SYSTEM OPEX COSTS

System Opex Costs

Hydro, OK WWTP Actual Metered Electrical Usage—2014

Hydro, OK WWTP
Feasibility Study by third party engineering firm evaluating the installation of surface aerators and disinfection on existing lagoon

Component HP Required Hours Operated/Day Days Operated/Year KWH Req./Year
(@ 0.746 KWH/hp)
Estimated Cost/Item
(assume $0.1/KWH)
           
Four-10 hp surface aerators 40 24  365 261,398 $26,140
Influent pumping 5.4 5.8 365 8,528  $853
Chlorination Mixing/Pumping 2 24 365 13,070 $1,307
Dechlorination Mixing/Pumping 1 0.58 365 6,535 $654
Estimated OM&R         $48,741
Estimated Labor         $25,028
Total Annual KWH       289,531  
Estimated Annual Operational Cost         $102,723

 

Hydro, OK WWTP
Actual operating cost associated with BiO2 Solutions technology

Component HP Required Hours Operated/Day Days Operated/Year KWH Req./Year
(@ 0.746 KWH/hp)
Estimated Cost/Item
(assume $0.1/KWH)
           
8 tank greenhouse utilizing 8 growth lights @ 430 W   10 365 12,556 $1,256
Eight-2.84 KWH heaters (22.7 KWH)   10 150 34,050 $3,405
48 microbubble diffuser units powered by 12 compressors Twelve 1/3 hp compressors (4 hp) 24 365 26,140 $2,614
EC Technology (50 gpm)—includes all components       76,314 $7,631
Estimated OM&R         $21,600
Estimated Labor         $18,000
Total Annual KWH       149,060  
Estimated Annual Operational Cost>         $54,506


Hydro WWTP savings: $48,217/year (140,471 KWH/year)